Tell us about your next solar project

Send the project size, location, structure type and programme dates — we'll come back with crew size, output and availability.

Programme estimator

Estimate your installation programme

Indicative figures for structure and module installation including torquing and marking, based on our typical output of 5–6 MW per team per month.

Duration with our standard 5-team crew7–9 weeks
Teams needed for your window5 teams
Approx. people on site~30

Indicative only. Actual output depends on site conditions, structure complexity and module clamp type. We confirm figures after reviewing drawings.